TimberTech AZEK Deck Replacement with Metal Railing in Boise

TimberTech AZEK Deck Replacement with Metal Railing in Boise

Boise 10 ft × 16 ft (160 sq ft)

Quick answer

Iron Crest Remodeling Group LLC completed this deck builder project in Boise. Iron Crest tore out an aging painted wood deck, its built-in bench and its steps at a Boise home and built a new 10 × 16 foot (160 sq ft) TimberTech AZEK composite deck from the ground up: six new concrete footings, 4×4 pressure-treated posts on galvanized post bases, a new 2×8 pressure-treated frame, TimberTech AZEK decking with hidden fasteners, two step runs down to the lawn, and 36-inch black metal railing.

Project Overview

Iron Crest tore out an aging painted wood deck, its built-in bench and its steps at a Boise home and built a new 10 × 16 foot (160 sq ft) TimberTech AZEK composite deck from the ground up: six new concrete footings, 4×4 pressure-treated posts on galvanized post bases, a new 2×8 pressure-treated frame, TimberTech AZEK decking with hidden fasteners, two step runs down to the lawn, and 36-inch black metal railing. Job photos show the old decking stripped on June 17, 2026, the new frame up on June 19 and the finished deck on June 21.

Deck Size
10 ft × 16 ft (160 sq ft)
Decking
TimberTech AZEK, hidden fasteners
Railing
36 in black metal, 30 linear ft
Foundation
6 new concrete footings
Framing
2×8 pressure-treated
Build Photos
June 17 → June 21, 2026

Planning something similar in Boise? Call (208) 779-5551 or use the form to request a free estimate.

Before & After

Drag the slider to compare the transformation of this deck builder project in Boise.

Before: original condition before deck builder

Before

After: completed deck builder

After

Project Photos

Before

Old painted wood deck with a built-in bench and wood steps behind a Boise home before replacement
Before (May 12): the painted wood deck with its built-in bench
Painted wood deck steps and bench on a Boise home before the TimberTech deck replacement
Before: worn painted boards and wood steps
Old deck boards removed exposing the original deck frame at a Boise home
Demolition (June 17): old decking stripped to the frame
New pressure-treated 2x8 deck frame on post bases and concrete footings in Boise
Framing (June 19): new 2×8 pressure-treated frame on new footings

After

New TimberTech AZEK composite deck with black metal railing and steps in a Boise backyard
After (June 21): TimberTech AZEK decking, black metal railing and steps
Finished Boise composite deck with two step runs, fascia and 36-inch black metal railing
After: two step runs down to the lawn
Side view of a new TimberTech composite deck with metal railing against a gray Boise house
After: hidden-fastened boards and matching fascia

The Challenge

The original deck was painted wood with a built-in bench and backrest along one side and wood steps down to the yard. Painted wood in Boise's climate — hot, dry summers with strong sun and freeze-thaw winters — needs regular scraping and repainting to stay presentable. Re-covering the old structure with new boards would have tied a new low-maintenance surface to an old frame, so the decision was to replace the entire deck, structure included.

Our Solution

We demolished and hauled away the existing deck, the built-in bench and the steps, then rebuilt from the footings up. Six new concrete footings carry 4×4 pressure-treated posts set on galvanized post-base brackets, which keep the wood off the concrete. The new frame is 2×8 pressure-treated lumber — a 16-foot rim board and fifteen 2×8 joists — set with joist hangers and structural connectors. The walking surface is TimberTech AZEK composite decking in a color the homeowner chose, fastened with a hidden-fastener system so the boards show no screw heads, and the rim is wrapped in matching fascia boards. Two step runs, framed in pressure-treated lumber and surfaced in the same decking, lead down to the lawn, and 36-inch black metal railing runs along the open sides in place of the old bench.

The Result

The homeowner has a new deck that does not need to be scraped, stained or painted: a new structure on new footings, a fastener-free TimberTech AZEK surface, clean fascia around the edge, black metal railing that keeps the view open, and two ways down to the yard. The build itself was quick — the job photos run from stripped decking on June 17 to a finished deck on June 21, 2026, in line with the 4–6 working day schedule in the contract.

How We Did It

1

Demolition & Haul-Away

Existing painted wood deck, built-in bench and steps torn out and hauled away; site cleaned and prepped for footings

2

Footings & Posts

Six new concrete footings with 4×4 pressure-treated posts on galvanized post-base brackets

3

Framing

New 2×8 pressure-treated frame — a 16-foot rim board and fifteen joists — set with joist hangers and structural connectors

4

Decking & Fascia

TimberTech AZEK composite decking installed with a hidden-fastener system; rim wrapped in matching fascia

5

Steps & Railing

Two step runs framed in pressure-treated lumber and surfaced in decking; 30 linear feet of 36-inch black metal railing

Key Features

Full replacement — footings, posts, frame and surface all new
160 sq ft TimberTech AZEK composite deck
Hidden fasteners: no screw heads on the walking surface
Matching fascia wrapping the deck rim
Two step runs down to the lawn
36-inch black metal railing in place of the old wood bench
No scraping, staining or repainting going forward
Photographed start to finish: June 17 to June 21, 2026

Materials Used

TimberTech AZEK composite decking (homeowner-selected color)
Hidden deck-fastener system
Matching decking fascia on the rim
2×8 pressure-treated rim board and joists
4×4 pressure-treated posts
Galvanized post-base brackets
6 concrete footings
Joist hangers and structural connectors
36-inch black metal railing (30 linear ft)

Deck Builder in Boise: Questions About This Project

What did Iron Crest build on this Boise deck project?

We removed an old painted wood deck, its built-in bench and its steps, and built a new 10 × 16 foot (160 sq ft) TimberTech AZEK composite deck on six new concrete footings, 4×4 pressure-treated posts and a new 2×8 pressure-treated frame. The boards are hidden-fastened, the rim has matching fascia, and the deck has two step runs and 36-inch black metal railing.

How long does a deck replacement like this take?

On this project the job photos show the old decking stripped on June 17, 2026, the new frame built by June 19 and the finished deck on June 21. The contract scheduled 4–6 working days, weather permitting. Larger, elevated or attached decks take longer, and permit review time comes on top of construction.

Do you need a permit to build a deck in Boise?

The City of Boise requires a building permit when a deck is more than 12 inches above grade, according to the city's Homeowner's Guide. Other Treasure Valley cities and Ada County set their own thresholds, so check with the jurisdiction the property is in. Iron Crest confirms permit requirements for every deck during planning and pulls customary permits as part of the contract.

Should you re-deck an old frame or replace the whole deck?

Putting new boards on an old frame ties a new surface to whatever life the old structure has left. On this Boise project the whole deck came out and the footings, posts and frame were replaced along with the boards, so every part of the deck is new. Our deck replacement vs. resurfacing guide covers when re-decking can make sense.

What are hidden deck fasteners?

Hidden fasteners attach deck boards from the sides or below instead of screwing through the top face, so the walking surface has no visible screw heads. TimberTech makes several hidden-fastener systems for its decking; this deck was installed with a hidden-fastener system throughout.

Why use galvanized post bases under deck posts?

Post-base brackets anchor each post to its concrete footing and hold the end grain of the wood up off the concrete, where it would otherwise sit in water. On this deck every 4×4 pressure-treated post sits in a galvanized post base on a new footing.

Does a TimberTech AZEK deck need to be stained or painted?

No. Unlike the painted wood deck it replaced, the TimberTech AZEK boards are not stained or painted; routine cleaning is the maintenance.

Does Iron Crest build decks outside Boise?

Yes. Iron Crest Remodel designs and builds decks across the Treasure Valley, including Boise, Meridian, Eagle, Nampa, Kuna, Star, Caldwell and Garden City.